Publication More cost, less benefit for NSW: the flawed rationale for the Hunter Valley coal mine expansion
Executive Summary
The proposed Hunter Valley Operations (HVO) Continuation Project is the largest coal expansion project under NSW Government assessment. The HVO Joint Venture (51% Yancoal, 49% Glencore) is seeking to expand existing mine operations to 2045 and extract an additional hundreds of millions of tonnes of run-of-mine coal (ROM) over the coming decades.
HVO Joint Venture’s original proposal sought to extract an additional 684 million tonnes (Mt) of ROM coal, which would have resulted in an estimated 32 Mt of CO₂-equivalent (MtCO₂e) direct emissions within NSW, and nearly 1 gigatonne of CO₂-equivalent (GtCO₂e) from end-use combustion of coal in export markets. Following concerns raised by the NSW Government about the project’s significant fugitive methane emissions and impact on the State’s legislated emissions reduction targets [1], the joint venture is revising the application – reducing the mine size by 35% [2], resulting in 40% less scope 1 emissions [3] relative to the original proposal. The revised proposal is expected in mid-2025.
Even with a reduced size, the HVO Continuation Project represents almost 40% of emissions in the NSW Government’s coal project approval pipeline. With existing coal mining projects already straining the ability of NSW to meet its legislated emissions reduction targets, if HVO is approved it will further strain the state’s ability to meet its targets and shift the burden onto other sectors to make deeper emissions reductions.
A critical component of the assessment process will be consideration of the economic costs and benefits to NSW. ACCR has undertaken a detailed review of the cost-benefit analysis (CBA) [4] the HVO Joint Venture provided in 2024 as part of its original proposal. We found this 2024 CBA significantly understates the cost of emissions from the project, meaning it overstates its net economic benefits to the state.
When we applied the latest NSW Treasury guidance to the 2024 CBA, and considered the full scope of relevant emissions in NSW, the estimated net benefits to the NSW community reduced by 88% – from $7.84 billion to $0.94 billion [5]. Further, when we used a coal price forecast more aligned with federal and state commitments to the Paris Agreement, the project’s net benefits to the NSW community dropped below zero.
The insights gleaned from this analysis aim to inform a more robust and credible CBA for the upcoming revised application. A CBA which uses the most up-to-date guidance, includes all relevant emissions, and considers coal price assumptions consistent with government commitments to the Paris Agreement will provide the NSW Government a more credible basis for decision-making.
Key Findings
- The 2024 cost-benefit analysis (CBA) undertaken for the proposed HVO Continuation Project significantly understates the cost of emissions to NSW, due to its reliance on an outdated framework. When the current Treasury framework is applied the cost of emissions is 1700 times higher, rising from $3.7 million to $6.34 billion. This sees the project's net benefits to NSW reduce by 81%, from $7.84 billion to $1.50 billion. See Chart 1.1 – (1).
The 2024 CBA uses NSW Treasury Guidance TPP17-03 as a framework to quantify the cost of carbon emissions of the project. This is in line with 2018 guidance from the Department of Planning, Housing and Infrastructure (DPHI). However, TPP17-03 has since been superseded by TPG23-08, which uses a NSW-specific Marginal Abatement Cost (MAC) and aligns emissions valuation with the state’s legislated emissions targets.
- The emissions estimate in the 2024 CBA excludes emissions from intrastate rail transport [6]. When these are included total emissions are 9% higher, resulting in an additional $0.56 billion in costs. When the current Treasury framework is applied to the full scope of emissions, the project’s net benefits to NSW are reduced by 88% compared to the 2024 CBA, falling from $7.84 billion to $0.94 billion. See Chart 1.1 – (2).
- The 2024 CBA relies on a coal price forecast that is considerably higher than the International Energy Agency’s (IEA) Announced Pledges Scenario (APS) and Net Zero Emissions (NZE) scenario. When the project’s benefits are modelled in line with the APS and NZE its direct benefits decline by 8% and 26% respectively. When the current Treasury framework is applied, and the full scope of NSW emissions is included, a Paris-aligned coal pricing forecast results in the project's net benefit to NSW falling below zero, which means it becomes a social cost to the state. See Chart 1.1 – (3A) and (3B).
The APS reflects the global policy direction based on announced government commitments, while the NZE scenario aligns with NSW and Federal commitments to the Paris Agreement.
Chart 1.1: Analysis of the 2024 CBA using the current Treasury Framework, the full scope of NSW emissions, and APS and NZE pricing shows a significant reduction in the project’s net benefits to NSW [7]
Source: 2024 CBA, TPG23-08, NSW Treasury Carbon values report, IEA WEO 2024 extended dataset, ACCR modelling
- If HVO is approved, it would materially affect the state’s ability to meet its legislated emissions reduction targets - including imposing a burden on other sectors to compensate with deeper cuts - yet the 2024 CBA does not account for this. Coal mining accounts for around 15% of total NSW emissions, which would increase to over 20% by 2035 if all proposed coal mining expansions are approved. The HVO Continuation Project accounts for almost 40% of coal expansion emissions in NSW under consideration.
Recommendations
ACCR recommends that any future application for the HVO Continuation Project must include a cost-benefit analysis that incorporates:
- The latest NSW Treasury guidance, TPG23-08, to ensure emissions are costed appropriately and the State’s emissions targets are reflected in the assessment.
The NSW Government should assess all projects – public and private – using consistent methodologies. TPG23-08 is mandatory for assessing public investments and should be applied to private investments to ensure the consistency and integrity of planning processes. Project assessments should be based on sound economic analysis and not subject to differential treatment based on ownership.
- The full scope of emissions occurring within NSW, including intrastate rail emissions.
- The project's direct benefits under future energy scenarios, consistent with federal and state commitments to the Paris Agreement and aligned with the expected policy direction.
The impact of each recommendation on project value to NSW has been modelled by ACCR and is labelled accordingly in Chart 1.1.
Download a PDF of More cost, less benefit for NSW: the flawed rationale for the Hunter Valley coal mine expansion | 23/07/2025
Please read the terms and conditions attached to the use of this site.
NSW DPHI, Consideration of Climate Change (Net Zero Future) Act 2023, Scope 3 Emissions and Mining Panel Advice, letter to HVO Pty Ltd, July 2024. ↩︎
ACCR estimate based on a reduction of ~220 Mt ROM coal relative to the original proposal. HVO Pty Ltd, Response to RFI and Proposed Project Amendments, letter submitted to the NSW DPHI, March 2025, p. 4. ↩︎
HVO Pty Ltd, Response to RFI and Proposed Project Amendments, letter submitted to the NSW DPHI, March 2025, p. 5. ↩︎
Ernst and Young (EY) published a revised Economic Impact Assessment in May 2024 which included the cost-benefit analysis of the project to the NSW community. ↩︎
Unless otherwise stated, all monetary values in this report are expressed in Australian dollars (AUD). ↩︎
Under current NSW Treasury guidance all emissions that occur within NSW should be included in a cost-benefit analysis. ↩︎
Numbered labels in the chart correspond to the key findings and recommendations. ↩︎